Project Timeline
This timeline will be updated as new information becomes available. Due to the nature of construction, this timeline is subject to change.
February 2011
Demolition of the old clinic building; waste will be removed from the site and 90 percent of it will be recycled.
March through September 2011
Excavation for the underground parking structure
October 2011 through August 2012
Construction of the building, including exterior finishes
September 2012 through May 2013
Interior construction, including installation of utilities, technology systems, medical equipment and interior finishes
August 2013
Anticipated opening
A Message to our Neighbors
PAMF is committed to being a good neighbor and will work to address any issues that may arise during the demolition of the old building and construction of the medical center. If you have any questions or concerns about work at the site, please call PAMF’s Sunnyvale Hotline at (408) 523-3950 or e-mail our Public Affairs Manager Cynthia Greaves at greavec@pamf.org.